Friday, February 20, 2026

☀️ Solar Plant HT Evacuation – Detailed Checklist & SOP

☀️ Solar Plant HT Evacuation – Detailed Checklist & SOP

High Tension (HT) evacuation is a critical backbone activity in any solar power plant. Proper design, installation, testing, and protection coordination directly impact plant efficiency, safety, grid compliance, and long-term reliability.


⚡ A. HT Evacuation – Design & Planning Checklist

1️⃣ System Design & Grid Approval

✔️ HT voltage level finalized (11 kV / 22 kV / 33 kV) as per DISCOM approval
✔️ Approved Single Line Diagram (SLD) available and stamped by DISCOM
✔️ Short-circuit level study completed and verified
✔️ Protection philosophy finalized (selectivity & coordination ensured)
✔️ Redundancy philosophy (Ring / Radial / Dual source) defined
✔️ Provision for future plant capacity expansion incorporated


2️⃣ Transformer Planning & Placement

✔️ Inverter Duty Transformer (IDT) located close to inverter blocks to minimize LT losses
✔️ Pooling / Main Transformer positioned near load center or switchyard
✔️ HT cable / overhead (OH) line route optimized for minimum length and losses
✔️ Sufficient clearance for maintenance & ventilation ensured
✔️ Proper RCC foundation with oil soak pit / bund wall (if oil-filled transformer)
✔️ Neutral earthing arrangement finalized (resistor/solid earthing as applicable)


3️⃣ HT Cable / Overhead Line Selection

✔️ Conductor size selected based on current carrying capacity, voltage drop & thermal limits
✔️ Insulation class matching system voltage (e.g., 12 kV / 24 kV / 36 kV class)
✔️ Technical loss calculations validated
✔️ Soil resistivity & temperature considered for cable derating
✔️ Proper laying method (direct buried / trench / cable tray / HDPE duct) defined
✔️ Cable route markers & identification plan prepared


4️⃣ HT Switchgear & Protection System

✔️ VCB / RMU rated as per system fault level
✔️ Protection relays configured (OC, EF, UV, OV, REF, Differential if applicable)
✔️ CT/PT ratios correctly selected and verified
✔️ Numerical relay settings approved and documented
✔️ Protection coordination study with DISCOM grid completed
✔️ Mechanical & electrical interlocking logic tested


5️⃣ Earthing & Lightning Protection

✔️ Substation earth resistance within permissible limits (typically <1 ohm)
✔️ Separate earth pits for equipment body, neutral, and lightning arresters
✔️ Transformer, structure, panel earthing continuity verified
✔️ LA installed at line entry & transformer HT/LT side
✔️ Earth grid interconnected and bonded properly


⚡ B. SOP – HT Evacuation Execution

🔹 Step 1: Pre-Execution Preparation

✔️ Approved drawings (SLD, layout, earthing, protection) available at site
✔️ Material inspection & test certificates verified
✔️ Calibration certificates of torque wrench & testing equipment available
✔️ HT safety tools (insulated gloves, discharge rods, rubber mats) available
✔️ Valid work permit & shutdown approval obtained


🔹 Step 2: Installation

✔️ Transformer installed on leveled foundation with correct alignment
✔️ Anchor bolts tightened and torque values recorded
✔️ HT cable bending radius maintained as per manufacturer guidelines
✔️ Correct phase sequence maintained throughout system
✔️ Terminations (heat shrink / cold shrink) executed by trained personnel
✔️ Proper gland earthing & double earthing ensured


🔹 Step 3: Jointing & Terminations

✔️ Approved HT joint kits used
✔️ Conductor surfaces cleaned, oxide removed, and contact grease applied
✔️ Proper crimping tools with correct dies used
✔️ No exposed strands or insulation damage
✔️ Stress control components installed correctly


🔹 Step 4: Testing & Commissioning

✔️ Insulation Resistance (IR) test conducted and recorded
✔️ Hi-Pot / VLF test for HT cables performed
✔️ Transformer ratio, polarity & vector group verified
✔️ Protection relay secondary injection testing completed
✔️ Earth resistance measurement recorded
✔️ Functional checks of breaker trip & close circuits done


🔹 Step 5: Charging & Energization

✔️ Area barricaded and access restricted
✔️ All protection systems in service
✔️ First energization under no-load condition
✔️ Voltage, current & relay indications monitored
✔️ Checked for abnormal sound, vibration, or heating
✔️ Load gradually applied after stability confirmation


⚡ C. Mandatory Safety SOP

✔️ Only authorized and trained personnel permitted
✔️ PPE mandatory: helmet, arc-rated gloves, safety shoes, face shield
✔️ Lock-Out Tag-Out (LOTO) procedure strictly followed
✔️ Live working strictly prohibited
✔️ Danger boards & signage installed at all HT locations
✔️ Emergency response & first aid kit available


⚠️ D. Common Mistakes to Avoid

❌ Oversized HT route increasing losses & cost
❌ Poor termination workmanship leading to partial discharge
❌ Inadequate earthing or improper bonding
❌ Protection mismatch with DISCOM grid settings
❌ Ignoring future expansion provisions
❌ Improper torque or absence of torque marking


🔑 Key Takeaway

HT evacuation is not just about transferring power to the grid — it directly impacts:

✔️ Plant efficiency
✔️ Electrical safety
✔️ Grid compliance
✔️ Operational reliability
✔️ Long-term asset life

A well-designed and properly executed HT system ensures smooth commissioning, minimal downtime, and sustained performance of the solar power plant.


https://www.youtube.com/channel/UC4_D50vMu1wbQrPaLFYo6Eg https://www.youtube.com/channel/UC4_D50vMu1wbQrPaLFYo6Eg RRB JE, SSC AE/JE UPSSSC JE, SSC JE, CIVIL ENGINEERING MCQs, ELECTICAL ENGINEERING MCQs, preavious year quesion papers, dmrc, lmrc, drdo,rrb ntpc, ntpc, pgcil, dsssb, states board, GATE IES EE, ESE, ECE, ME, CE, IT & CS EXAM MATERIALS & OLD PAPERS Electrical Engineering https://t.me/pravendrarajpoot Daily news & current affairs in hindi & english fully updated Daily current affairs https://t.me/newsdailypkr Engineering Discussion group for your upcoming exams, you can ask your any query regarding your problem,👇👇👇 https://t.me/joinchat/JObxeA7n6S4qvnegrGhTgA PKR ELECTRICAL ENGINEERING I am sure this is the best place for you guys subscribe and get success IF YOU WANT TO JOIN ME ON TELEGRAM FOR PDF @newsdailypkr AE/JE EE, ESE, ECE, ME, CE, IT & CS EXAM MATERIALS & OLD PAPERS Electrical Engineering https://t.me/pravendrarajpoot facebook page:- Pravendra Kumar Rajpoot https://t.me/newsdailypkr https://chat.whatsapp.com/5AS7dNFTP4H4vVsiWsqHrT https://t.me/srk50 https://t.me/pravendrarajpoot https://t.me/joinchat/JObxeA7n6S4qvnegrGhTgA https://t.me/pravendrarajpoot Daily news & current affairs in hindi & english fully updated Daily current affairs https://t.me/newsdailypkr Engineering Discussion group for your upcoming exams, you can ask your any query regarding your problem,👇👇👇 https://t.me/joinchat/JObxeA7n6S4qvnegrGhTgA PKR ELECTRICAL ENGINEERING I am sure this is the best place for you guys subscribe and get success IF YOU WANT TO JOIN ME ON TELEGRAM FOR PDF @newsdailypkr AE/JE EE, ESE, ECE, ME, CE, IT & CS EXAM MATERIALS & OLD PAPERS Electrical Engineering https://t.me/pravendrarajpoot facebook page:- Pravendra Kumar Rajpoot https://t.me/newsdailypkr https://chat.whatsapp.com/5AS7dNFTP4H4vVsiWsqHrT https://t.me/srk50 https://t.me/pravendrarajpoot https://t.me/joinchat/JObxeA7n6S4qvnegrGhTgA

No comments:

Featured Post

MAJOR 10 PANDEMICS (MAHAMARI) IN HISTORY

OUTBREAK: 10 OF THE WORST PANDEMICS IN HISTORY BY PRAVENDRA KUMAR RAJPOOT Scientists and medical researchers have for years have dif...